What Is a Section 278 Agreement? A Complete Guide for Developers
When you need one, the seven stages, how long it takes, what it costs and who builds the works. For developers in England and Wales.
A Section 278 Agreement (S278) is a legal agreement between a developer and the highway authority, made under Section 278 of the Highways Act 1980. It allows permanent alterations to an existing public highway that a development needs, such as a new junction, road widening or a pedestrian crossing, with the developer paying for the works and the authority's costs.
Planning permission does not replace it. No work can start on the public highway until the agreement is signed, the bond is in place and the authority's pre-commencement requirements have been met. This guide explains when an S278 is needed, what it covers, the seven stages of the process, how long it takes, what it costs and who builds the works.
Key facts at a glance
| The law | Highways Act 1980, Section 278 |
| Applies in | England and Wales |
| Who you agree it with | The highway authority for that road: usually the county, unitary, metropolitan or London borough council. National Highways for motorways and trunk roads in England, the Welsh Government for trunk roads in Wales, and Transport for London for London's red routes |
| What it covers | Permanent alterations or improvements to an existing public highway |
| Who pays | The developer: the works, plus the authority's design-check, legal, inspection and administration costs |
| Who builds the works | Usually a highways contractor appointed by the developer and accepted by the authority. Some authorities build the works themselves |
| Is planning permission enough? | No. Highway approval is a separate process |
| When can work start? | Only once the agreement is signed, the bond is in place and pre-commencement requirements are met |
| How long to get the agreement? | Several months. Birmingham City Council quotes about 6 months on average from receipt of the initial fees |
| Related agreements | Section 38 (adoption of new roads) and Section 184 (vehicle crossings) |
What is a Section 278 Agreement?
Section 278 of the Highways Act 1980 lets a highway authority agree with any person that highway works will be carried out at that person's expense, provided the authority is satisfied the works will benefit the public.
On paper, the authority carries out the works and the developer pays. In practice, most authorities use the agreement to let the developer's own contractor work on the public highway as if the authority were doing the work itself. Birmingham City Council, for example, says it normally uses S278 agreements this way, with the developer responsible for everything from design through to supervising construction.
The agreement sets out the approved drawings, the programme, the fees, the bond, the inspection regime and what must happen before the authority takes the finished works back into its own maintenance.
Planning permission is not highway approval. A scheme can have full planning consent and still have no right to touch the road outside the site.
When is a Section 278 Agreement required?
You need a Section 278 Agreement when a development requires permanent changes to an existing public highway. The requirement usually comes from the planning permission itself, through a planning condition or a planning obligation. Those conditions often prevent the development from being occupied, or sometimes even started, until the highway works are complete. That makes the S278 a critical-path item for the whole project.
Typical projects involving Section 278 works include:
- Residential developments: new junctions, road widening and access arrangements for housing estates.
- Commercial developments: highway changes to serve offices, retail parks and business premises.
- Industrial developments: new or upgraded entrances designed for heavy goods vehicles.
- Retail developments: junction improvements, pedestrian crossings and turning lanes.
- Schools and public buildings: improvements to pedestrian safety, vehicle access and traffic flow.
- Transport infrastructure: traffic signals, cycleways, bus stops and associated improvements.
When you don't need one
Not every job that touches a road needs an S278.
- A dropped kerb or single vehicle crossing is normally dealt with under Section 184 of the Highways Act 1980, through the council's vehicle crossing application.
- New estate roads inside your site that you want the council to adopt are dealt with under Section 38.
- Temporary items such as hoardings, scaffolding or materials on the highway need their own licences.
Some authorities also offer a simplified "minor works" agreement for small schemes. The highway authority decides which route applies.
What types of work are covered by Section 278?
Section 278 works range from a simple access alteration to a major junction scheme.
- New junctions and access points. Priority junctions, bell-mouth entrances, right-turn lanes, roundabouts and signal-controlled accesses.
- Road widening and highway improvements. Extra capacity, better visibility or room for larger vehicles.
- Traffic signals and pedestrian crossings. New or altered signals and crossings, which usually need traffic modelling and road safety audits.
- Footways and cycleways. New footways, shared-use routes, crossing points and links to existing networks.
- Highway drainage and street lighting. Where the alterations affect gullies, drainage runs, lighting columns or signs, these form part of the works.
- Supporting changes. Road markings, signs, kerbing, resurfacing, and any Traffic Regulation Orders needed for speed limits, waiting restrictions or parking bays.
How does the Section 278 process work?
Every highway authority has its own procedure, but the process follows the same seven stages.
Step 1: Early discussion with the highway authority
Talk to the authority before you design in detail. Most authorities encourage an informal approach, and many offer paid pre-application advice. This establishes the scope of the works, the standards that apply and any problems with the layout.
Check the authority's rules on timing. Birmingham City Council, for example, will not consider a formal S278 submission until planning approval is in place.
Step 2: Detailed highway design
The design must meet the authority's standards, not just the planning drawing. Depending on the scheme, the submission may include:
- Highway layout and construction drawings
- Topographical survey
- Drainage design
- Vehicle swept-path analysis
- Traffic signal and street lighting designs
- Road safety audits (Stage 1 at preliminary design and Stage 2 at detailed design)
- Traffic management proposals
- Utility and underground service information
Step 3: Technical approval
The authority checks the design and issues comments until it is satisfied. Expect more than one round on anything beyond a simple access. Incomplete submissions are the most common cause of delay at this stage.
Technical approval is not permission to start work.
Step 4: Legal agreement and bond
The agreement is drafted, the fees are paid and financial security is provided. The developer normally pays the authority's legal costs as well as its own.
The authority will require a performance bond or cash deposit so that it can finish the works if the developer does not. Birmingham City Council sets this at 110% of the cost of the highway works, including utility works.
Step 5: Pre-construction approvals
A signed agreement still isn't a start date. Before work begins, you will usually need to:
- Confirm the appointed contractor and their insurance and street works qualifications
- Book road space or obtain a permit for the works
- Agree temporary traffic management
- Progress any Traffic Regulation Orders
- Agree street lighting changes and any tree works
- Obtain separate licences for hoardings, scaffolding or materials on the highway
- Arrange the authority's inspections
Step 6: Construction
The works are built to the approved drawings and the authority's specification. The authority's inspector visits at agreed stages, and work that is covered up before inspection may have to be opened up again.
Step 7: Completion, maintenance period and handover
The authority inspects the finished works and lists any defects. A Stage 3 road safety audit is carried out on completion. Once defects are cleared, the authority issues its completion certificate and a maintenance period begins, commonly 12 months, during which the developer remains responsible for defects.
At the end of the maintenance period, the authority carries out a final inspection, issues the final certificate, releases the remaining bond and takes over maintenance of the works.
How long does a Section 278 Agreement take?
Allow several months to get the agreement signed, and longer for complex schemes. There is no statutory timescale.
Birmingham City Council states that, on average, completing an S278 agreement takes about 6 months once the initial fees have been received. It says the exact timing depends on the complexity of the scheme, the completeness and quality of the designs, how quickly information is supplied and how fast the legal work progresses.
Other things that add time:
- Road safety audits and the design changes they lead to
- Utility diversions, which run to the utility companies' own programmes
- Traffic Regulation Orders, which involve statutory consultation
- Restrictions on when road space is available
That time covers the agreement only. Construction, the maintenance period and final handover come afterwards.
How to avoid delays
- Start the S278 as soon as the planning position allows. Do not wait until the build is under way.
- Submit a complete package first time.
- Order utility diversions early.
- Bring a highways contractor in before the design is fixed, so buildability, traffic management and phasing are dealt with on paper rather than on site.
How much does a Section 278 Agreement cost?
The developer pays for everything: the works, the design, and the authority's costs of checking, approving and inspecting them. There is no standard price, because the works themselves vary from a simple access to a signalised junction.
Budget for these categories:
| Cost | What it covers |
|---|---|
| Design and professional fees | Surveys, engineering design, road safety audits, traffic modelling |
| Highway authority fees | Pre-application advice, technical approval, inspection and administration |
| Legal costs | Your solicitor's fees and the authority's |
| Construction | Excavation, road construction, kerbing, surfacing, drainage, lighting, signs and markings |
| Traffic management | Temporary signals, lane closures and pedestrian diversions |
| Utility diversions | Protecting, moving or altering existing services. Often the least predictable cost |
| Performance bond | Security for completion of the works |
| Commuted sums | A payment towards future maintenance of certain assets, where the authority requires it |
A worked example: Birmingham City Council's published charges
These are Birmingham City Council's published figures for 2026/27, checked on 15 November 2026. Other authorities set their own charges, often as a percentage of the works cost, so always check the current schedule for the authority concerned.
| Item | Birmingham City Council, 2026/27 |
|---|---|
| Pre-application advice (minor application, up to 25 housing units equivalent) | £1,732 |
| Application check before technical approval | £173 |
| Minimum technical approval and inspection fee (schemes over £15,000 construction value) | £15,348 |
| Performance bond or cash deposit | 110% of the cost of the highway works, including utility works |
| Commuted sum, where applicable | Maintenance and renewal costs for 30 years |
If an amount due under a Section 278 Agreement is not paid, the Act gives the authority strong remedies. It can direct that the access or other works are not used until the amount is paid, and the debt can be made a charge on the land.
At Section278Works.co.uk, part of R W Services Contractors Ltd, we can help developers assess the practical construction requirements of their highway works, price them and plan the delivery programme.
What is the difference between Section 278 and Section 38?
Section 278 is for changing an existing public road. Section 38 is for getting a new road adopted. Both come from the Highways Act 1980.
| Section 278 | Section 38 | |
|---|---|---|
| Applies to | An existing public highway | A new road built by the developer, usually on the developer's land |
| Purpose | Alter or improve the highway to serve the development | Have the new road adopted as a highway maintainable at public expense |
| Typical example | The new junction onto the main road | The estate roads inside the site |
Most housing schemes need both: a Section 38 Agreement for the internal estate roads and a Section 278 Agreement for the junction that connects them to the existing network.
Who carries out Section 278 works?
In most cases the developer appoints a highways contractor, and the highway authority must accept that contractor before work starts. In other cases the authority builds the works itself and recovers the cost. The agreement says which applies.
Either way, the developer funds the works and carries the obligations in the agreement.
Authorities typically ask for evidence of street works (NRSWA) qualifications, public liability insurance and relevant highway experience. The exact requirements vary by authority and by scheme.
Why use an experienced Section 278 contractor?
Section 278 works are built on live public roads, in front of road users, neighbours and the authority's inspector. An experienced highways contractor can:
- Assess the practical scope of the works before the design is fixed
- Coordinate with designers, consultants and the highway authority
- Prepare realistic construction budgets and programmes
- Plan traffic management and safe working arrangements
- Build the works to the approved specification
- Manage inspections and clear defects quickly
- Support completion, the maintenance period and final handover
R W Services Contractors Ltd delivers Section 278 works for developers, housebuilders and commercial projects, from access improvements to larger highway schemes.
Frequently asked questions
Is a Section 278 Agreement a legal requirement?
Yes, where your development needs permanent works on an existing public highway and the highway authority requires them to be delivered under Section 278. You have no right to carry out those works without the agreement.
Can I start work before the Section 278 Agreement is signed?
No. Work on the public highway can only start once the agreement is signed, the bond is in place and the pre-commencement requirements are met. Technical approval alone is not permission to start, and authorities can take legal action over unauthorised works.
Does planning permission include Section 278 approval?
No. Planning permission and highway approval are separate. A development can have full planning consent and still need a Section 278 Agreement before any highway works begin.
Who pays for Section 278 works?
The developer. That covers construction, design, the highway authority's checking, inspection, legal and administration costs, the bond and any commuted sum for future maintenance.
Who is the highway authority for a Section 278 Agreement?
Usually the county, unitary, metropolitan or London borough council. For motorways and trunk roads in England it is National Highways, for trunk roads in Wales the Welsh Government, and for London's red routes Transport for London.
How long does a Section 278 Agreement take?
Several months, and longer for complex schemes. Birmingham City Council quotes about 6 months on average from receipt of the initial fees. Construction and the maintenance period follow afterwards.
Do I need a Section 278 Agreement for a dropped kerb?
Usually not. A domestic dropped kerb or vehicle crossing is normally handled under Section 184 of the Highways Act 1980 through the council's vehicle crossing application. Larger commercial accesses and development-related junctions normally need a Section 278 Agreement.
What is the difference between Section 278 and Section 38?
Section 278 covers alterations to an existing public highway. Section 38 covers the adoption of new roads built by a developer. Many developments need both.
What happens if Section 278 works fail inspection?
The defects must be put right before the authority issues its completion certificate. Until then the maintenance period does not start and the bond is not reduced, so failed inspections cost both time and money.
Do Section 278 works need a specialist contractor?
In practice, yes. Highway authorities expect contractors working on the public highway to show relevant experience, street works qualifications and adequate insurance, and many will only accept contractors they have approved.
Does Section 278 apply in Scotland or Northern Ireland?
No. Section 278 of the Highways Act 1980 applies in England and Wales only. Scotland and Northern Ireland have separate roads legislation.
Need help with Section 278 works?
If your development needs a new junction, access improvements, road widening or other changes to an existing public highway, early contractor input can save months later.
Section278Works.co.uk is part of R W Services Contractors Ltd, providing specialist highway construction for developers, housebuilders and commercial projects. Tell us about your development, the location of the works and your programme.
Section 278 Works, part of R W Services Contractors Ltd
294 Aldridge Road, Streetly, West Midlands, B74 2DU
This article is general guidance for projects in England and Wales. Requirements vary between highway authorities and individual agreements. Confirm the requirements for your scheme with the relevant authority and your professional advisers.
Related guides
- What Is a Section 38 Agreement? Road Adoption Explained Coming soon
- Road Safety Audits Explained: Stages 1 to 4 for Section 278 Works Coming soon
Sources
- Highways Act 1980, Section 278: legislation.gov.uk
- Highways Act 1980, Section 38: legislation.gov.uk
- Highways Act 1980, Section 184: legislation.gov.uk
- Work on public highways: Section 278 agreements: Birmingham City Council, checked 15 November 2026 (timescales page updated 1 April 2026, fees page updated 9 April 2026)